© L. Lesley 2005
TRAM Power Ltd.,
Unit 4 Carraway Road,
Liverpool L11 OEE
Tel: +44 (0)151 548 7040 Fax: +44 (0)151 546 6066
email: Lesley@trampower.co.uk web: www.trampower.co.uk
CONTENTS
The LR55 tramway track system was invented in 1989 and provides continuous support for running rails, through the use of precast concrete foundation troughs. The LR55 rail transmits static and dynamic loads, from tramcars and road vehicles, at the head of the rail rather than the foot. The LR55 troughs rest on a prepared and compacted highway road base layer. The LR55 rails are bonded into the troughs by an elastomeric grout. By these means the high wheel/rail contact stress is distributed to the base of the trough, typically with a pressure into the road base of below 100 kN/m2.
1.2 Testing
The LR55 tramway track system has been subjected to rigorous testing. A model based on a finite element analysis has been constructed and validated by laboratory and field tests. Additionally laboratory tests have simulated 200 million axles passes of up to 80 tonne loading and 100km/hr. Two separate field trials have been undertaken. The first in Rotherham Bus station between 1993 and 1995. The second began in March 1996 in the South Yorkshire Supertramway and is now part of the permanent infrastructure.
1.3 Purpose of Method Statement
This METHOD STATEMENT is intended to provide contractors with a systematic guide to the safe and accurate installation of the LR55 tramway track system in urban highway environments. By following this guidance, LR55 tracks will be capable of carrying tramcars and all road vehicles, safely, and with a durable long life low maintenance installation.
1.4 The LR55 system
The LR55 tramway track system is designed to be installed in any road or highway with a minimum of preparation, disruption and after treatment, The total depth of the LR55 tramway track system is less than 200mm and so a minimum of excavation and disturbance to existing highway pavements is required. Further because the LR55 precast concrete foundation troughs are stiff and interconnected, one rail can be laid at a time and normally rails do not need to be gauge tied. This means that with the agreement of under street utility agencies, apparatus deeper than 200mm from the road surface can be left in situ, since access between rails and tracks is physcially available. Finally the LR55 track is self supporting over trenches 1m wide, enabling utility repairs and maintenance to be undertaken with a minimum of disturbance to tramway operations.
1.5 LR55 components
The LR55 track system consists of a new asymmetric rail section (Fig. 1), where static and dynamic loads are principally transmitted at the rail head level into the concrete foundation trough. Not only does this ensure that the wheel contact stresses are widely distributed as a low pressure along the length of the underside of the concrete foundation trough but also is a stable rail section with virtually no turning moment due to tram sway or bogie hunting. The LR55 rail includes an integral flange way or groove which substantially reduces the risks of tram derailment, and allows all road vehicles to be accommodated, as with older grooved girder rail profiles, eg. Ri 60. The groove is compatable with all existing wheel flanges.
The LR55 rail is bonded into the upper surface of a precast concrete foundation trough (Fig. 2), which is supplied to site in lengths up to 12 metres as the installation specification requires. The troughs are pre-stressed during manufacture, and are symmetric, so can be used for either rail. The specification of the trough is set out in Appendix 1.
1.7 Bonding Grout
The LR55 rails are bonded into the troughs with an elastomeric grout. Two types of elastomeric grout have been tested with the LR55 track system. The SIKA KC330 grout has been tested in laboratory and at the Rotherham site and found to be satisfactory, replicating earlier tests undertaken by the University of Calgary. The more recent SIKA KC340 is a UK Railtrack plc type approved development of the KC330 (see Appendix 2).
The second elastomeric grout tested was the ALH system 6. This was subjected to a series of laboratory and field tests, like the KC330. It was also found to be satisfactory for the wheel loads and speeds of tramways. It was used for the Supertramway installation.
Fig. 2 LR55 Pre-cast Pre-stressed concrete trough
The LR55 track system maintains gauge through the lateral stability of highway pavements. The lateral pressures on the external vertical faces of the LR55 foundation troughs are very low , typically under 20kN/m2, well below the compressive yield stress of flexible pavements. additional to this there is a shear force between the bottom of the trough and the bedding layer. In pavements displaying plastic failure, remedial work will be required, as detailed in 1.10, 2.0 and 6.3, before the installation of LR55 tracks.
1.9 Maintenance
Once the LR55 rails have been bonded into the foundation troughs, the roadway provides a flush pavement surface without any up stands, suitable for all other highway users. The rail has been designed so that as it wears, no remedial work, apart from some rail regrinding, is needed to maintain a flush road surface.
1.10 Pavement surveys
Prior to the LR55 track being installed in an existing highway, as a new track, surveys will be needed to establish the line, level and present state of the highway pavement. In a highway with a failing pavement, eg. plastic deformation, exposure of the bearing or base courses, pot holes etc., a remedial pavement repair programme is needed, to provide a safe surface for road vehicles and other users. Even if no remedial pavement works are needed, the pavement level may require re profiling to accommodate the line and level of LR55 tramway tracks. These works can be undertaken as conventional pavement contracts.
When existing girder railed tracks are replaced, a similar check on pavement state and level should be undertaken to confirm that it can accommodate the line and level of LR55 tracks.
Before the installation of the LR55 track system, the following information is needed:
Existing highway and tramway track plans should be checked for accuracy, especially line and level of track and crown of pavement.
2.3 Site Investigation
An investigation of the highways along which LR55 tracks will be laid, or replace existing girder railed tracks, needs to ensure that the bearing course or similar pavement layer 200mm below the road surface has a CBR better than 3%, or a strength of at least 100kN/m2.
This investigation will also identify the location and nature of all under street utility plant which will be beneath the LR55 tracks, especially any plant physically in the space to be occupied by the LR55 troughs.
2.4 Survey Results
The results of these investigations will determine what, if any, remedial measures are needed. The most likely are:
The design of the LR55 track installation will take into account the existing or expected nature and volume of road vehicular traffic, the nature of the tramway services intended, including the location of tram stops or stations, and the need to provide servicing accommodation for frontagers, where alternative off street or side street provision is not possible. The design will also take into account the need of the owners of under street utility plant for access for maintenance or repair, including the procedures for repairs during continuing tramway operations.
This design involves two stages:
For (a) this design will involve co-operation with traffic and highway engineers to ensure that anticipated volumes of road traffic can be accommodated safely. This will include road junction layout, kerb splays, traffic signal/tram signal location and sight lines, tram stop access and any interaction with nearby bus stops, both in vehicular terms and for the convenience and safety of interchanging passengers. It will also include the swept part of tramcars to ensure safe passing distances between tramcars, from fixed street furniture and equipment, and other road vehicles.
For (b) where an existing road is already trafficked by buses or heavy goods vehicles, without any signs of pavement distress or failure, then the track designer with the responsible highway engineer can be confident that the existing highway pavement can support LR55 tracks without any structural strengthening. The only preliminary works required may the re profiling of the pavement to accommodate the line and level of tramway tracks.
3.2 Pavement strengthening
Where there is any doubt about the strength of the existing pavement, or its stability, conventional pavement tests can be used as a preliminary to replacement with a conventional flexible or rigid design, for a life of 20 years or more. As a further check on pavement stability, a finite element model is available to confirm LR55 track stresses, and pressures on the highway pavement from the LR55 concrete foundation troughs.
The LR55 rail, precast concrete foundation trough and elastomeric bonding grout specification and requirements have been established by comprehensive testing, and will be confirmed as satisfactory by the relevant highway authority and tramway operator.
4.2 LR55 Rail
The LR55 rail will be sourced from a recognised steel rolling mill, produced to the required profile (eg. Fig. 1) using a rail grade steel.
4.3 Rail examination
Before welding into long lengths, the LR55 rails must be examined to ensure there is no physical damage, no microscopic cracking, occlusions or other imperfections. The LR55 rails can be welded into long lengths by flash butt or Thermit techniques. After welding the LR55 rails will be ultra sonically tested to ensure that the welds are structurally sound.
Where a length of LR55 rail is to be welded to a section previously installed into a LR55 concrete trough, a section of rail at least 1 metre long should be left unbonded, to enable the new LR55 rail to be welded without damaging the bonding grout of the already bonded LR55 length.
4.4 LR55 Foundation Troughs
Pre-stressed and precast LR55 concrete foundation troughs of approved cross section (Fig, 2), are manufactured from >40N grade concrete. The troughs should conform to the specification of the relevant highway authority for concrete products used in highway pavements, eg. drainage gullies etc..
4.5 Elastomeric Grout
The elastomeric resin grout to bond the LR55 rails into the concrete foundation troughs will be based on a polyurethane composition, like SIKA KC330 (Appendix 2) or ALH System 6, and satisfy the requirements for bonding, durability and resistance against water and chemical decomposition.
Prior to the installation of the rails, the trough interiors needs to be cleaned, removing loose debris, and be dry and grease free. The trough may also need to be treated with a primer compatible with and sympathetic to the elastomeric bonding grout to be used.
5.2 Rail priming
Prior to installation the underside of the LR55 rails must be cleaned to remove scale, rolling superficial flaws and rust. This can be achieved eg. by shot blasting. The underside of the rails are then painted with the primer required for bonding with the elastomeric grout. This can be undertaken off site, and provided that the underside of the LR55 rails is undamaged when delivered to site, a final application of primer can be applied shortly before bonding into the LR55 concrete foundation troughs.
The LR55 concrete foundation troughs must be installed on a properly compacted bedding layer, in pre dug trenches (200mm deep and 400mm wide) in the highway pavement. The bedding layer consists of an asphaltic sand, dry lean mix (1:4) or similar to provide full contact between the base of the trough and the pavement. The line and level of this bedding layer is critical to the final and satisfactory line and level of the track. A cross section general arrangement of installed LR55 track in a highway pavement is shown in Fig. 3.
Fig. 3 General arrangement of LR55 track installation
The following clauses set out the detail of installing the LR55 track system
6.3 Pavement works
The LR55 track system allows an existing tramway track to be replaced whilst maintaining tramway services, by means of over night possessions, provided that the existing horizontal alignment is being maintained, since existing drainage arrangements can also be retained. The existing track foundation slab can be used with an appropriate bedding layer (6.1 above) to give good contact with the LR55 foundation troughs. Each existing rail can replaced singly with a LR55 rail and trams operating temporarily on a mixture of running rails.
Using a disc cutter, or a pair of discs in tandem, a width of 400mm across an existing grooved girder rail is delineated with cuts at least 200mm deep. This will cut the gauging bars between rails which can be left in situ after rail replacement. The old grooved girder rail is pulled out with the cut pavement using a backactor or similar, to create a trench the required size for LR55 foundation troughs. The bottom of the trench is cleaned up with a narrow bucket backhoe or similar to give a clean 200mm minimum depth. A bedding layer (6.1) is introduced and compacted to the right line and level for the final LR55 track installation. The LR55 troughs are then installed (6.6)
Where a completely new installation is planned, preparatory works will include the relocation of any under street utility plant, eg. magnetic vehicle loop detector cables, etc., which are physically in the space required for LR55 troughs. Generally utility plant deeper than 300mm can be left in situ, provided the utility authorities are satisfied over repair and maintenance access.
Where the existing highway pavement shows signs of premature failure under road traffic, or its expected life is significantly less than that of the LR55 tramway tracks to be installed, then the Highway Authority should repair the pavement in advance of the LR55 track laying, as the easiest and lowest cost option, using a conventional highway contract. Where a new pavement profile is needed, the tramway authority will need to co-operate with the Highway Authority to ensure that the new pavement has the correct profile, whether or not relaying for structural purposes is required.
Drainage of LR55 tracks will need to be accommodated by the use of groove drains at low points in the track, or by surface drains between rails at low points. These drains will discharge into the exiting highway drainage system, which should have sufficient capacity since the catchment area is increased. In normal operation tramways do not use dangerous chemicals and so no pollution of drains will take place. On hills some tramcars use sand to increase adhesion on wet tracks. The volumes are generally small but with other road debris can present problems of blocking the drainage system. New tramway drainage arrangements are designed to prevent ponding and therefore maintain the safety and convenience for other road traffic.
Using disc cutters and backhoe excavators, or single pass trenching machines, trenches 400mm wide and at least 200mm deep are cut into the existing highway pavement. One trench is required for each LR55 rail. The trench will be marked out and dug using laser guidance or similar to ensure the correct alignment of the track and ultimately the correct gauge between rails. This can be achieved in a new installation by laying one rail to line and level, and using that as a datum for the other rail(s), including track and clearance gauges.
Once the accommodation trenches have been cut (6.4), a suitable bedding layer, eg. asphaltic sand, dry lean (1:4) mix or similar, is compacted at the bottom of the trench. The compaction must provide a bearing strength of 3% CBR (or at least 100kN/m2). The final compacted level and line also determines the LR55 foundation trough line and level. The tops of the LR55 troughs need to be flush with the pavement surface. The tolerance of the top of the LR55 troughs should be agreed with the Highway Authority, typically a maximum of 5mm, as this will determine the tolerance that needs to be achieved by the bedding layer.
On the prepared bedding layer, in the pre dug trenches set out above, the LR55 precast concrete foundation troughs are laid to track level. The troughs are designed for mechanical handling, and can be lifted directly off a delivery vehicle in a single operation, to minimise the possession time of the highway and the disruption to traffic. The LR55 troughs abut each other end to end, and are linked with stainless steel clips to maintain alignment, prior to the bonding of the LR55 rails. The LR55 troughs provide continuous support to the LR55 rails. The LR55 troughs are set out to a lateral tolerance of 5mm. Curved track and transitions are accommodated by straight troughs cut to length with chamfered ends and laid as tangents around the curve. Switches and crossings are accommodated with specially cast switch and crossing LR55 troughs, eg. 25m radius and 1:2.9 crossing angle.
With the LR55 foundation troughs laid to line and level (and gauge) in the accommodation trenches, the troughs are sealed into the highway pavement with a suitable compound like bitumen. This will provide structural integrity between the troughs and pavement, and ensure full resistance against water ingress.
A transition rail will be used to connect the LR55 section to an older grooved girder rail section. Designs for transitions between LR55 and other rail sections, eg. Ri59, Ri60, 80lb, UIC60, Bullhead etc. are available, to enable castings to be obtained. The transition rail is asymmetric, with left and right hand pieces, and a splayed flangeway for joining non grooved rail sections. The correct piece must be used, butt welded off site to the first LR55 section. The other end of the transition rail is then clamped to the older rail end, and then welded using the Thermit or similar process, or temporarily fishplated, prior to further LR55 installations.
Ideally LR55 rails should be welded off site into long strings (eg. 200m), where quality control can be better. This will reduce the time of a possession in the street when the LR55 track is installed. Bent or damaged rail should not be used. On site the LR55 rail string should be welded to the end of the last LR55 laid rails, or to a transition if joining an older section of track (6.8). Where necessary, rails will be bonded to earthing cables, when stray current control is especially critical. The rails and welds should be set out so that rail welds do not coincide with joints between troughs, to prevent "hinges" being created. The LR55 rails will either be installed one trough at a time, or both rails simultaneously. In both cases proper care will be taken to ensure that the rails are set out to the correct line, level and gauge. This will be achieved by:
The LR55 rails well be set out to achieve a tolerance of line, level and gauge of better than 0.5mm. LR55 rails will either be set out at a neutral temperature, or a required tension applied mechanically along the LR55 rails to compensate for possible thermal expansion.
The alignment of each LR55 rail, and together the track, will be ensured by measuring the versine on the running edge of the inside of the LR55 rails:
The track gauge will be measured and confirmed at 3 metre intervals along the track, as will any required cant, level and alignment.
The elastomeric grout is injected into the void beneath the LR55 rail, until the grout completely fills the space between the LR55 trough and LR55 rail to the upper level of the LR55 trough (Fig. 3). In injecting the grout care is taken to ensure that all surfaces are dry and grease free, and that all extraneous materials have been removed. The injection of grout must also ensure that the space is totally filled and that no air is trapped or voids created. This can be achieved by a single pass injector incorporating a hot air jet blowing out material and drying the LR55 trough and underside of the LR55 rail in advance of the bonding grout.
The relative proportions between the bonding grout resin and curer will be adjusted according to the manufacturers specification to compensate for ambient temperature and to achieve the minimum injection time required before the resin solidifies and achieves traffic bearing strength. It is anticipated that the injection of the elastomeric grout will not be a batched operation but that the resin and curer will be mixed continuously as the grout is injected to ensure the maximum practical time. The resin/curer mix will also be based on the anticipated time before traffic will pass over the LR55 tracks. Typical mixtures can reach 80% full strength within 4 hours of mixing and injecting.
In case 6.9(a) the grout can be injected in a single operation. This will incorporate the pre-cured wedges integrally with the bonding grout.
In case 6.9(b) there will need to be two passes of grout injection. The first to locate the LR55 rail firmly in the LR55 trough. When cured sufficiently to carry the weight of the LR55 rails, the clamps and frames are removed and a final injection of grout bonds the LR55 rails right up to the top of the LR55 trough.
If another method of rail setting out is used, an agreed method of grout injection must be approved by the tramway authority. In all cases care must be taken to ensure that no air is entrapped in the grout, and that the grout makes full contact between the open surfaces of the LR55 rails and LR55 troughs.
In wet weather precautions like tenting the work area, should be used to ensure that the bonding surfaces remain dry until the grout is fully cured. On a graded alignment, bonding should begin at the highest point, so that in wet weather, any rain in the LR55 troughs runs away from the location of grout injection.
Where skid resistance is considered to be a problem, eg. approaching traffic signals, then materials like aluminium oxide can be spread on top of the grout prior to final curing, to provide a higher skid resisting surface.
The LR55 track must be checked to ensure that the elastomeric grout has fully filled the LR55 trough, without voids, and firmly bonds the LR55 rail into the LR55 trough. The inspection should check that there are no signs of the grouting delaminating, and that the grout has filled the interstitial space between the vertical faces of the ends of adjacent LR55 troughs, which provides an additional axis of rigidity.
Where a new LR55 track is laid and a rail end has been left ungrouted to enable additional troughs and rails to be added, care will be take to ensure that the exposed LR55 rail and LR55 trough are not disturbed before the additional troughs and rails are added. If necessary the exposed trough should be temporarily plated over, and care taken to ensure that the bedding layer is not disturbed.
Normally LR55 rails will be extended from LR55 troughs and LR55 rails made ready prior to the extension, by means of a temporary termination (8.0). In all cases the exposed troughs will be inspected to ensure that they are undamaged and retain the designed line and level. The exposed LR55 rails will also be inspected to ensure that these are also undamaged. In both cases re-priming will be needed to ensure good bonding is obtained with the elastomeric grout.
Where existing older grooved girder railed track is being replaced by LR55 track, the temporarily ungrouted LR55 rail end will be joined to the older track by a clamped transition rail and a temporary highway diversion away from the rail join.
The most likely repair requirement will be due to a failed weld between sections of LR55 rails. In the LR55 system the ends of the weld will be supported by the grouting in the LR55 trough, so there is little danger of the rail ends separating and endangering the operational integrity of tramcars.
To repair the broken weld, the grouting on either side of the weld for a distance of 1 metre must be removed, by a high pressure water cutter or similar. If the cause of the weld break is an originally faulty weld, then a reweld using the Thermit or other approved method can be executed. If the failure is compounded by thermal contraction forces, then a measure of compensation must be incorporated by jacking or other techniques.
Once the reweld has been completed, the site must be cleaned up, and the LR55 rail and trough re primed. New grout can them be injected to bond the LR55 rail to be trough and to ensure good adhesion with the existing grouting on either side of the reweld site.
Should the resin grouting be found to be delaminating from the LR55 foundation trough or the LR55 rail, then grouting for a distance of 500mm either side of the extremity of the delamination site should be removed by high pressure water jetting or other approved method. The LR55 trough and LR55 rail need to be cleaned, debris removed, the site dried and re primed. Finally new grout can be injected at the site to bond LR55 rail to LR55 trough and to ensure a sound bond with the existing set grout.
If the LR55 trough is superficially damaged at the exposed road surface it can be repaired with a resin based cement mortar, which has a quick setting time. If the LR55 trough is structurally damaged, then it must be replaced. A length of each adjacent LR55 trough needs to have the grouting delaminated by water jetting or similar, The LR55 rail is then cut 500mm outside the damaged trough. The damaged LR55 trough and cut LR55 rail are then removed together.
The bedding layer is checked, or remade and re compacted as necessary. A new LR55 trough unit is inserted to replace the damaged trough and joined to the adjacent troughs. The LR55 rail retrieved from the damaged trough, or a new length of LR55 rail is then welded to the existing LR55 rails by the Thermit or butt weld process. Finally the LR55 rail and exposed troughs are cleaned and primed, and new grouting injected to ensure a sound bond.
When the LR55 rail head wears more than the specified tolerance (eg. 10mm), it may be restored by electric arc welding of the rail head. This is offered as a commercial service by a number of companies. Many tramway operators also have it as an in house technique. When sufficient new metal has been deposited on the rail head, it is ground down to the required profile. A similar technique can be use to rebuild a worn rail side, with subsequent regrinding to profile. This is a long established technique and should not damage or degrade the bonding grout.
If the wear is such that it has reduced the structural integrity of the bearing flanges (below 5mm thickness), then the LR55 rail should be replaced, using the procedure set out in 9.2. At that time the LR55 troughs should also be assessed for surface wear or damage, which would indicate the replacement of both rail and trough, using the procedure in 9.4.
The preparation of the highway pavement, including any remedial works to extend pavement life or re profile should be undertaken in accordance with the relevant design standards and specification of the local or national Highway Authority as appropriate.
The process for excavating the required trenches at least 200mm deep and 400mm wide should be agreed with the Highway Authority, especially over traffic rerouting and possession times. The impact of these can be minimised by installing one rail at a time or the use of over night possession, where a sequence of activities from trench cutting, LR55 trough installation, LR55 rail location and welding, injecting the bonding grout and release back to road traffic can ensure progress at the rate of at least 100m per overnight possession.
The trenches can be excavated some time in advance of the installation of LR55 troughs, using temporary steel plates to cover the trenches, which allow road traffic to operate during the day. In excavating these trenches it is important to remove all loose road pavement material and to have as clean sides and bottom as possible.
The bedding layer should be installed in stages to ensure the correct compaction (CBR > 3%) and line and level. With practice a LR55 installation team will learn the correct amount of bedding material and the degree of compaction required to achieve the necessary strength, line and level.
The LR55 foundation troughs should conform to the design (Fig 2) and relevant specification, for example that drawn up by Marshall's for the LR55 trough (Appendix One)
The cross section of the LR55 rail should conform to the detail of the drawing set out in Fig 1, or another approved for the purpose, allowing variation of groove width and depth and rail head curvature. The LR55 rail should be rolled from an acceptable rail grade steel.
The bonding grout should satisfy a specification like that for SIKA KC330 or KC340 (Appendix Two), or ALH System 6. If another proprietory polyurethane two pack resin grout is proposed, then the tramway designer and installer should satisfy themselves of the adhesion, elasticity, electrical resistivity, durability and resistance to chemical or ultra violet degradation.
One: Marshall LR55 foundation trough
Two: SIKA specification for KC340
Fig. 1 LR55 rail cross section
(b) New LR55 tracks
6.4 Accommodation trenches
6.5 Bedding layer compaction
6.6 LR55 foundation trough
6.7 Sealing LR55 troughs into pavement
6.8 Permanent connections to existing track
6.9 LR55 rail welding and alignment
6.10 Setting out and checking
6.11 LR55 rail bonding into LR55 trough
7.0 Inspection
7.1 After installation.
8.0 Temporary terminations
9.0 Extensions, repairs, replacement
9.1 Extensions
9.2 Broken Welds
9.3 Grouting delamination
9.4 Trough damage
9.5 Worn LR55 rails
10.0 Design and material standards
10.1 Highway pavement and drainage
10.2 Rail trenches and bedding layer
10.3 LR55 foundation troughs
10.4 LR55 rails
10.5 Bonding grout
APPENDICES
GENERAL ARRANGEMENT DRAWINGS